CCWEL cycleway (Roseburn) construction 18 months from May 2020 with support for local businesses

Community Council News
Plan of Traffic Regulation Order designs for CCWEL (c) City of Edinburgh Council

According to the mins of 5 Nov 2019 (quoted here):

"P Gregson reported that he had attended the meeting arranged by the Council with local traders to discuss support for their businesses during the construction phase of the CCWEL. The contractor’s representatives and Cllr Douglas had attended the meeting. The support offered involved publicising the businesses by various methods including social media. The construction work is scheduled to start in May 2020 and take 18 months. It will involve closing the right turn from Roseburn Terrace into Roseburn Street for a period of 12 weeks. The Council is expected to hold a further meeting with the traders."