Event details
The various diversion notices can be found here.
According to Karolina Baran, City Council Engineer,
"The Coltbridge Viaduct refurbishment works are on the way and progressing well.
However, to repair timber steps along the SW wing wall, we are going to close the steps for approx. 3 weeks, 10/02-28/02. Attached are signs that we will be placing at the various points on approach to the steps to catch members of the public from all areas.
To avoid any further disturbance, the timing / duration of the closure will also coincide with the striking and dismantling of Span 1 scaffolding which is a hazardous task to passers-by beneath the SW wing wall."
Karolina Baran MEng CEng MICE | Engineer - Structures | Place | Planning and Transport | The City of Edinburgh Council | Level G.4, Waverley Court | 4 East Market Street | Edinburgh EH8 8BG| karolina.baran@edinburgh.gov.uk | www.edinburgh.gov.uk